The Tesla Berlin plant received permission to start construction for 90 hectares

via:博客园     time:2020/5/30 16:41:04     readed:75

orgsrc=//img2020.cnblogs.com/news/66372/202005/66372-20200530153356519-1425115897.jpg

Tencent technology news, May 29, according to foreign media reports, Tesla's Berlin plant in Brandenburg, Germany, the electric vehicle manufacturer, has obtained the preliminary construction permit from the National Environment Agency of the country and can start infrastructure construction.

Tesla will now be allowed to stay at Glenn G

Tesla has been allowed to level the area and store construction materials transported by trains there. According to the German National Environment Agency, any construction work should be carried out on the aquifer, which is a permeable rock mass containing or transporting groundwater. This measure will protect drinking water from chemicals or other potentially harmful substances.

According to the recently issued permit, construction vehicles on the construction site must be refuelled outside the drinking water protection area, and noise measurement will be carried out to keep the construction personnel following the local guidelines. In January, Tesla's team was asked to stay below a specific noise level when they were removing trees from the site.

On working days, construction work is allowed between 6 a.m. and 10 p.m. The license also states that Tesla will be at its own risk of implementing these measures. The project has not been fully approved because some parts of the project cannot be carried out until measures to maintain safe social distance are cancelled. Residents are allowed to express concerns about ongoing construction projects near their residences, but restrictions on new crown prevention measures are not conducive to people gathering.

Some local government officials have suggested an online conference, but this is not in line with German rules, because not every citizen has access to the Internet. The meeting is expected to take place some time soon, but it may wait until Germany removes the epidemic-restricting rules, when collective gatherings may resume.

This certification from the German National Environment Agency marks the third time Tesla has obtained early construction permits for projects related to the Berlin plant. The first is the permit to move trees, the second is to prepare the foundation and excavation permit. Tesla has taken full responsibility for the plot, which means that if the project is rejected for some reason, the company will be required to restore the soil to its original state.

Tesla expects the Berlin plant to be completed in July 2021 and will initially be used to produce Model Y. cross-boundary vehicles The plant, which is expected to employ 12,000 employees, is expected to have a significant positive impact on the German economy. (Tencent Science and Technology Reviser / Jinlu)